What is a WIP schedule? (And why your bank keeps asking for one)

A WIP (work-in-progress) schedule is a report that lists every active job with its contract value, costs to date, estimated cost to finish, percent complete, revenue earned, and amount billed — so you can see, job by job, whether you're ahead, behind, overbilled, or underbilled. It's the single most important report in construction accounting.

By Brian Harmon, Founder of Builder Ledger · Construction controller for 10+ years

Why It Matters

Your P&L is lying to you. Your WIP isn't.

Here's the problem with a regular profit-and-loss statement in construction: it only knows what you've billed and what you've spent. Bill a job early and the month looks great — even if the job is bleeding. Spend heavy before your first draw and the month looks terrible — even if the job is perfectly on track. The P&L moves with your billing timing. The WIP moves with reality.

A WIP schedule fixes that by measuring every job against its own budget using percentage-of-completion: how much of the work is actually done, how much revenue that work has truly earned, and how that compares to what you've billed. It's how your bank decides how much credit you deserve, how your surety decides how much work you can bond, and how smart owners decide which jobs deserve their attention this month.

Anatomy of a WIP

What every column actually means.

📝

Contract Value

The current contract amount — original contract plus approved change orders. Unapproved change orders don't belong here until they're signed; counting them early is how margins get overstated.

💰

Costs to Date

Every dollar of job cost incurred so far — labor, materials, subs, equipment. This only works if costs are coded to the job when they happen, not swept up at month-end.

🔮

Estimated Cost to Complete

What it will take to finish the job from today. This is the most honest number on the schedule — and the one that gets "managed" when someone doesn't want to report bad news.

📐

Percent Complete

Costs to date ÷ total estimated cost (costs to date + cost to complete). Spend $270K of a $450K total budget and you're 60% complete — regardless of what the billing says.

✅

Earned Revenue

Percent complete × contract value. This is the revenue the job has actually earned, and it's what belongs on an honest P&L — not the billing total.

⚖️

Over / Under Billing

Billed to date minus earned revenue. Positive means you've billed ahead of the work (overbilled). Negative means you've done work you haven't billed for (underbilled) — and financed it yourself.

Worked Example

One job, start to finish.

Say you have a $500,000 contract. So far you've spent $270,000, and your best estimate says it will take another $180,000 to finish. Here's the WIP math:

LineAmountHow you get it
Contract value$500,000Contract + approved change orders
Costs to date$270,000Job cost ledger
Cost to complete$180,000PM/controller estimate to finish
Total estimated cost$450,000$270,000 + $180,000
Percent complete60%$270,000 ÷ $450,000
Earned revenue$300,00060% × $500,000
Billed to date$330,000Progress billings sent
Overbilled$30,000$330,000 billed − $300,000 earned

Read it like an owner: the job is 60% done, on budget ($450K total cost against a $500K contract = a planned 10% margin), and $30,000 overbilled — you've collected ahead of the work, which is good for cash but means $30,000 of future work is already spoken for. If that "cost to complete" quietly should be $230,000 instead of $180,000, the job is actually heading for a loss — and the WIP is the only place that shows up before the job ends.

Where WIPs Go Wrong

The five mistakes that cost contractors money.

1

Optimistic cost-to-complete

The PM doesn't want to report a problem, so the estimate to finish stays rosy until it can't. Margin fade hides here. Fix: review the estimate against actual production every month, with someone who isn't the PM.

2

Unapproved change orders in the contract value

Counting unsigned change orders inflates earned revenue and makes a losing job look fine. Fix: contract value changes only when the change order is approved. Track pending COs separately.

3

Costs coded late (or to the wrong job)

If job costs land weeks late — or on the wrong job — percent complete is fiction. Fix: weekly cost coding discipline, and a month-end cutoff that's actually enforced.

4

Ignoring chronic underbilling

Underbilled jobs mean you're financing your customer's project. A little is normal; a pattern is a cash leak. Fix: flag any job underbilled two months running and find out why.

5

Building the WIP once a year

An annual WIP — built for the CPA or the bonding renewal — is archaeology. By the time you see the problem, the job is over. Fix: monthly. No exceptions. It's a management tool first, a reporting tool second.

6

Nobody reconciles it

The WIP should tie to the general ledger: earned revenue, billings, and job costs all reconciled. If it floats free of the books, your bank will notice before you do.

Who Reads Your WIP

Three audiences, one schedule.

Your surety uses it to size your bonding capacity — sloppy or stale WIP schedules are a classic reason bonding gets capped. Your bank uses it to judge your line of credit and whether your reported income is real. You should be using it first: it's the earliest-warning system you have for margin fade, billing gaps, and cash trouble. If the only time your WIP gets built is when someone else asks, you're reading your own business last.

FAQ

WIP questions, answered straight.

What does WIP stand for?

+
Work in progress — the value of work performed on jobs that have started but aren't finished yet. A WIP schedule measures every active job's percent complete, earned revenue, and over/under billing position.

How often should a WIP schedule be updated?

+
Monthly, at minimum. A WIP built once a year for taxes or bonding is archaeology — it describes jobs that are already over. Updated monthly, it's an early-warning system for margin fade and cash problems while you can still fix them.

What's the difference between a WIP schedule and a P&L?

+
A P&L reflects what you've billed and spent, so it swings with billing timing. A WIP schedule measures earned revenue by percent complete — what the work itself has actually produced. In construction, the WIP is the truer picture.

What does it mean to be overbilled on a job?

+
You've billed more than the revenue the job has earned by percent complete. It's good for short-term cash but means part of your future work is already collected and spent — the money to finish has to come from somewhere.

Who needs to see my WIP schedule?

+
Your surety (it sizes your bonding capacity), your bank (it supports your credit line and validates reported income), your CPA (for percentage-of-completion tax and financial statements) — and you, monthly, before any of them.
Go Deeper

Get the free WIP checklist — or have it handled.

Download the free Builder Ledger WIP checklist and audit your current schedule line by line. Or skip the homework: Builder Ledger prepares and reconciles a bank and surety-ready WIP for contractors every month, as part of a flat-rate controller engagement starting at $2,000/mo.

Month-to-month  ·  No long-term contract  ·  Contractors doing $1M–$20M